恆大室內裝飾施工工藝和質量標準

如需獲取資料,添加關注,轉發,私信回覆“施工資料”

目錄

第一章 住宅室內裝修工序間歇及工藝間歇標準······························3

1.1牆面各工序間歇及工藝間歇要求標準··································· ········3

1.2地面各工序間歇及工藝間歇要求標準············································3

1.3木地板施工基層要求標準································································4

1.4細部處理各工藝間歇要求標準························································4

1.5其它裝修施工要求············································································4

第二章 住宅室內裝修工藝流程標準·····················································5

第三章 住宅室內裝修施工工藝和質量標準····························· ···········6

3.1場地移交····························································································6

3.2彈線···································································································10

3.3電線穿管····················· ······································································14

3.4臥室地面找平···················································································15

3.5牆面磚鋪裝·······················································································17

3.6牆面石材鋪裝···················································································23

3.7天花吊頂、石膏線安裝·····································································28

3.8入戶門安裝·······················································································31

3.9地面磚、石材鋪貼·············································································34

3.10窗臺石鋪貼·····················································································40

3.11天花牆面扇灰、塗飾乳膠漆···························································42

3.12牆面造型製作、安裝·······································································47

3.13櫥櫃、衛浴安裝················································································51

3.14戶內門安裝······················································································57

3.15木地板安裝······················································································63

3.16牆面玻璃鏡面安裝·········································································70

3.17牆面木飾面造型油漆·····································································70

3.18牆紙貼鋪·························································································73

3.19陽臺護欄安裝·················································································77

3.20低窗護欄安裝·················································································78

3.21牆面軟包製作安裝·········································································80

3.22燈具、插座開關面板安裝·······························································82

3.23衛生潔具安裝·················································································97

3.24衛浴五金安裝···············································································104

3.25淋浴隔斷安裝···············································································105

3.26細部處理·······················································································106

3.27石材鏡面處理···············································································114

3.28衛生清理·······················································································116

恆大地產集團

住宅室內裝修施工工藝和質量標準

施工工序原則:先上後下、先溼後幹、先內後外、先粗後細、先製作後安裝。

第一章 住宅室內裝修工序間歇及工藝間歇標準

1.1牆面各工序間歇及工藝間歇要求標準

≥28天 ≥28天 ≥15-20天 ≥7天

工藝要求 工藝要求 工藝要求


1.2地面各工序間歇及工藝間歇要求標準

1、臥室木地板、地毯等基層地面找平完成後,可上人作業間歇時間為不小於48小時。

2、客廳、餐廳、廚房、衛生間、陽臺、電梯前室、首層大堂等地面磚、石材鋪貼完成後,可上人作業間歇時間為不小於48小時。

3、室內地面磚、石材及地面找平完成後,牆面1米線以下牆體刮裝飾膩子需要間歇不小於15-20天,其要求含水率不大於14﹪。

1.3木地板施工基層要求標準

木地板地面基層含水率標準一覽表

地區

季節

春、夏

≤12﹪

≤8﹪

秋、冬

≤8﹪

≤8﹪

1.4細部處理各工藝間歇要求標準

1、廚房、衛生間、陽臺、電梯前室、首層大堂等牆面磚採用溼貼工藝,磚縫水泥清理所需間歇時間為3-6小時。

2、牆面、地面、檯面等溼貼作業完成後,需鑽孔、打眼等間歇時間不小於14天。

3、各交界面細部處理打膠後,與衛生清理間歇時間不小於24小時。

4、入戶門門框安裝後,門扇安裝所需間歇時間不小於72小時;戶內門門框安裝後,門扇安裝所需間歇時間不小於24小時。

1.5其它裝修施工要求

1、小高層結構至8層,中高層、高層結構施工至12層,砌體開始施工時,裝修施工單位定標、不少於2名裝修管理人員到位。

3、外立面裝飾完成10層,外腳手架拆除上面5層,且衛生清理完畢,進行場地移交,裝修施工人員全部到位。

4、小高層分2批移交,每批5層,移交間歇時間15天;中高層、高層分3批移交,第1批5層,第2、3批移交10層左右,流水施工作業。

第三章 住宅室內裝修施工工藝和質量標準

3.1場地移交

3.1.1室內場地移交

1、室內結構樓板、牆面無穿透性裂縫和滲漏水缺陷。

2、室內天花結構板無下撓,平整度誤差不大於8mm,梁底兩端高差不超過8mm,模板接縫處應磨平。

3、牆體砌築、批蕩(衛生間、廚房牆面為1:2水泥砂漿,其餘牆面為混合砂漿)完成,基層無空鼓、開裂、起灰等質量缺陷,房間牆面陽角部位需做不低於2米高1:2水泥砂漿護角,垂直度、平整度誤差不大於3mm。

4、鋁合金門、窗框安裝到位,窗臺兩端尺寸誤差不大於10mm,陰陽角方正偏差不大於4mm,窗框塞縫完畢且淋水試驗合格,無窗框滲漏水。

5、廚房、衛生間、陽臺等給排水管線預埋及給水管試壓合格。

6、廚房煙道安裝並掛網批蕩,掛網與牆體搭接150mm,防水封堵和止回閥安裝完畢且驗收合格,煙道排煙口頂至樓板底高度為150mm。

7、強弱電預埋管線、底盒位置與設計圖紙一致,管線暢通。

8、隱蔽水電管道位置應標識清楚。

9、高位空調(臥室、書房)套管穿大於或等於700mm高的窗頂梁時,套管孔頂距梁底不大於220mm;穿剪力牆或砌體時套管孔頂距板底不小於400mm,且不大於600mm。

10、地面標高誤差控制在±10mm內,平整度偏差不大於8mm,陽

臺排水立管封堵和蓄水試驗完成,無滲漏水。

11、陽臺防水施工完畢且驗收合格。

12、戶內門洞尺寸滿足設計要求,門套兩側及頂部牆體砌築材料嚴禁為空心砌塊,且厚度誤差不大於10mm。

13、北方地區地暖管施工、保護完畢。

14、衛生間沉箱回填施工完畢,給排水管口預埋定位準確。

15、飄窗鋁合金邊框與牆體收口需凹入牆體10-20mm。

16、室內各房間開間、進深尺寸偏差不大於10mm,對角線尺寸偏差不大於15mm,地面清理乾淨。

17、牆面必須彈出結構1米線基準點且定位準確。

18、外牆施工完成且腳手架拆除完畢。

19、每棟樓至少每五層需各有一處滿足裝飾施工使用的水源、電源接入口。

3.1.2電梯前室

1、結構樓板無穿透性裂縫和滲漏水缺陷。

2、天花結構樓板平整度誤差不大於8mm。

3、牆體砌築、批蕩(1:2水泥砂漿)完成,基層無空鼓、起灰等質量缺陷,垂直度、平整度誤差不大於3mm。

4、入戶門框、管井門框、防火門框、鋁合金窗框、風口百頁框、電梯門框、消防箱等安裝到位,管井門框、消防箱高出牆面基層(含保溫層)23mm(以牆磚結合層為10mm厚計算)。

5、電梯召喚箱底盒預留洞口定位準確。

6、地面標高誤差控制在±10mm內,平整度偏差不大於8mm,地面水管預埋完成,試壓後無滲漏,管井土建封堵完成,無滲漏水。

7、電梯前室方正,開間、進深尺寸偏差不大於10mm,對角線尺寸偏差不大於15mm。

8、牆面必須彈出結構1米線基準點且定位準確。

9、地面清理乾淨。

3.1.3首層大堂

1、天花板預留洞口封堵完畢且無滲漏水,消防管、強弱電、熱力管主管等安裝完成。

2、牆體砌築、水泥砂漿(1:2)批蕩完成,無空鼓、起灰等質量缺陷,垂直度、平整度不大於3mm。

3、首層入戶門框、管井門框、防火門框、電梯門框等安裝到位。

4、地面標高誤差控制在±10mm內,平整度偏差不大於8mm,地面水、電、暖管預埋完成,試壓後無滲漏。

5、首層大廳開間、進深尺寸偏差不大於10mm,對角線偏差不大於15mm。

6、牆面必須彈出結構1米線基準點且定位準確。

7、地面清理乾淨。

8、入戶大堂上層露臺防水處理,蓄水無滲漏。

3.2彈線

3.2.1地面標高定位線

1、彈出結構1米線。

2、確定地面完成面標高定位線,無地暖地區通常以結構1米線下935mm為±0.000;北方地暖地區通常以結構1米線下880mm為±0.000。

3、根據設計圖紙標註相對標高,定各空間地面相對標高。